Production OEE Performance

Enter Production Data

Enter your production and downtime data to calculate OEE.

minutes
Total scheduled production time.
minutes
Planned breaks such as lunch or tea.
minutes
Unplanned downtime such as breakdowns.
min/unit
Ideal time required to produce one unit.
units
Total units produced during operating time.
units
Units produced without defects.

Your OEE Result

Overall Equipment Effectiveness and component results.

OEE 0.0%

OEE Result

Enter production data and click Calculate OEE.

Availability 0.0%
—
Performance 0.0%
—
Quality 0.0%
—

OEE Formula

OEE is the product of Availability, Performance and Quality.

OEEAvailability×Performance×Quality
Availability Operating Time ÷ Net Planned Production Time
Performance (Total Units × Ideal Cycle Time) ÷ Operating Time
Quality Good Units ÷ Total Units Produced

How to Calculate OEE

Follow these simple steps.

1
Enter Planned Production Time Total scheduled production time.
2
Enter Break Time Planned breaks such as lunch or tea.
3
Enter Downtime Breakdown, changeover and other unplanned stops.
4
Enter Ideal Cycle Time Ideal time required to make one unit.
5
Enter Total & Good Units Total output and defect-free output.
6
Calculate OEE Get OEE and all three component results.

Practical Manufacturing Example

See how OEE is calculated using a real example.

Parameter Value
Planned Production Time 480 min
Break Time 30 min
Downtime 45 min
Operating Time 405 min
Total Units 900
Good Units 890
Final OEE Calculation OEE = — × — × — = —